Dear all,

In the "Project and Setup" app all the timebox with date has been filled with start and end date. I am currently in the explore phase while prepare is done and overdue. All the type of tasks in the prepare phase (task, requirement,...) are done with status done. Normally they are no open point anymore in the prepare phase, nevertheless when opening the "Overview" app, the dashboard is showing that I am still in Prepare phase while the current phase is past and overdue. You can see below screenshot.

Rayane_1-1729077397783.pngRayane_2-1729077421002.png

Rayane_0-1729077315653.png

 

Accepted Solutions (1)

Accepted Solutions (1)

Rayane
Explorer
0 Kudos

Hi,

It's working thank you so much!