Hello Workflow experts,

I have made changes on an existing Workflow working on Prod and I have created a new version of it. There are processes running on the old version. My question is: How can I make them run on the new created version ?

As soon as I continued running the task, I´m getting an error.

Thanks in advance for your help!

View Entire Topic
DominikTylczyn
Active Contributor
0 Kudos

Hello @Thierry_twist 

To my knowledge you can't. Workflows started in production before the change will continue with the old version. Only workflow started after the change will run with the new version. 

I think there is no way around that. Otherwise it would be all but impossible to keep workflow data consistent.

Best regards

Dominik Tylczynski

Thierry_twist
Discoverer
0 Kudos

Hi Dominik,

thanks for your prompt answer. So there is no possibility to update the tree structure of a running workflow, using like a function module , right ?
I was not able to make it run with the new version so far.

kind regards,

Thierry

 

DominikTylczyn
Active Contributor
0 Kudos

Hello @Thierry_twist 

You can't update a structure of a running workflow as far as I know. I'm not aware of any method to do that.

I'd also strongly discourage any such attempts as they are very likely to result in inconsistent workflow data.

What is the problem with keeping with SAP standard - introduce a new version for future workflow instances and let the already running ones finish with the existing version?