on 2006 Jul 12 3:03 PM
Hi,
I got an error in running the change run step in the process chain.
The error is "The action is locked by a change run".
Could this mean that the change run was running when this step in the process chain was invoked.
I have a process chain with multiple(4) parallel processes and I would like to know from you gurus the best way to model such a process chain. Should I keep just one attribute change run at the end of the complete process chain or should I let the change run after every PC (each of the 4).
Any inputs will be appreciated
Thanks & Regards
Sid
Siddhartha,
Exactly, you need to keep the change run process at the end of the PC. no need to run the change run for every master data flow.
check whether change run is running? check in RS12 for locked entries.
All the best.
Regards,
Nagesh Ganisetti.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Siddhartha,
Its better to have only one attribute change run and should be trigger after 4 Process chains are completed. You will not get any advantage having attribute change run 4 times.
Hope it Helps
Srini
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You should run attribute change run for all the process in the process chain in which you have Master data & hierarchies & that too at the end of the process .
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
70 | |
10 | |
10 | |
7 | |
6 | |
6 | |
6 | |
5 | |
5 | |
5 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.