on 2019 Jan 18 8:24 AM
Requirement:
Two or more data_flow need to be executed in parallel.
When ALL these data_flow are executed completely (either success or failed), then execute next data_flow.
Can it be done?
Below is illustration.
Below is further finding on how to use work_flow to acheive parallel + sequential process.
A few work_flow may be required, depending on requirement.
Scenario 1: Single work_flow is enough to achieve below requirement
Scenario 2: Nested work_flow are required to achieve below requirement:
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Noted. Thanks for advice.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.