Dear all,

I need to schedule a background job transfer the exchange rate and global settings from R/3 source system daily because in our scenario the exchange rates are maintained everyday in in R/3. Can anyone please let me know the job names for them which need to be scheduled? Thanks in advance.

Regards,

Sumit

Accepted Solutions (1)

Accepted Solutions (1)

former_member188975
Active Contributor
0 Kudos

Hi Sumit,

Using SE38 > RSIMPCURR you can set up the job from menu Program > Execute in background. This is the same as going from RSA1 > Modeling > Source System > Right click the R/3 source system > Transfer Exchange Rates.

Hope this helps...