on 2024 Oct 17 12:06 PM
Hello Experts,
Im facing some issue with a process order. Im trying to understand how to get the alternative resource in REO as shown in the picture below.
After sending the process order from Cloud, I can see the operation activity being created for individual order. In this I always see the resource type is default. I have already set up the resource type and resource for shaping.
If I insert the Shaping resource type inactiovity operations application then everything works properly. But it has to be done to each and every Order released to DM. Is there a way to assign the default resource as Shaping as soon as I release the order from S4.
KR,
Sayuj
Request clarification before answering.
Hi, see Specifying Custom Values of Resource Types for Process Orders.
Br, Manoel
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
74 | |
30 | |
9 | |
7 | |
7 | |
6 | |
6 | |
4 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.