Hi all,

I'm currently into an Agentry project and we are facing some issue over versionning the project. I know we can use the Agentry Share functionnality to keep different version of the project. However, this is not what we need because we need to Merge different part of the project.

Since the project files are binary, I don't see how it is possible to achieve Merging functionnality.

Anyone has a suggestion or a workaround to let the Agentry Share allow the merging in a versionning system.

Thanks

Accepted Solutions (1)

Accepted Solutions (1)

jason_latko
Advisor
Advisor
0 Kudos

Neilson,

Agentry merges need to be done manually using Team Share or using Import/Compare within the Eclipse Agentry environment.  I prefer using Import/Compare.  Export your current application to the file system, then load the current master application into Eclipse.  Right-click the Agentry project in the Project Explorer and go to "Compare With".  Choose your file that was exported.  Use the compare window to import definitions from your project into the master.  Then save the new project and store that in version control.