on 2012 Jan 25 9:04 AM
Hi,
Netweaver 7.00
We have the folowing for the transports
DEV - > QAL -> Pre-PROD -> Prod
Pre-prod is not very used
so the developpers want to use Pre-prod as quality for a new project
like below:
DEV -> Pre-prod -> QAL -> prod
is it possible to have the 2 paths together ?
Is it a good configuration ?
Thanks for your help
Request clarification before answering.
You can only setup one consolidation route, so you either have QA or pre-prod but not both..
You could set pre-prod as a separate delivery route (you'll need to import the transport in QA first)
Regards
Juan