Hi

We have requirement to split a message(a master structure that has data for multiple IDOCS of multiple IDOC Types) into 'n' IDOCs using multi-mapping. The mapping program works fine in Message Mapping & Interface Mapping test tabs. We see 1 message getting split into n IDOCS.

However , when ccBPM calls this mapping from transformation step , we do not see a output. All the multi line containers are empty(thats wat we could see from the workflow log).

We are stuck with no proper trace messages to look at . Any ideas how to resolve this ? we r on SP9 , N:1 mapping call works and a scenario configured for aggregating n IDOCS into 1 message succeeds, but not the reverse !!!

Thanks

Saravana

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member185751
Contributor
0 Kudos

Hi,

Also Check this oss note: 791352

This OSS note is for SP11. but you can try applying.

We are on SP10 and we applied this note to enable trace in DEV and TST systems.

Regards,

Sridhar

former_member185751
Contributor
0 Kudos

Hi Saravana,

Pls check if the OSS note helps: 825201

Regards,