We recently embarked on a SAP solution manger upgrade for one of our esteemed customer .
It’s a customer with a complex heterogeneous landscape with applications running on varied OS and DB platforms while at the same time the account its highly sensitive with very high expectations.
They were running on SAP Solution Manager 7.0 and as part of the contract they had to be at a 7.1l . The driving factor for the upgrade was the "SAP CHARM" implementation which was planned later which required the SAP Solution Manager product to be at a higher level.
After the initial kick off meeting with the stake holders it all came down to these three important requirements
Based on which we decided on few things
We embarked on the development upgrade 2 weeks in advance and as part of the initial prepare we understood that the Oracle client , Kernel and Database libraries needed an upgrade.
We also had to update the SLD to the latest along with several SAP notes that needed to be applied along the process of creating the stack for the upgrade .
Some of the activities required downtime so we wanted to put all these together in one downtime to avoid reaching out to the customer for further dowtime.
The learning were also taken forward in the production upgrade where we upgraded these three components much in advance so it did not impact our timelines for the production upgrade.
The uptime processes were optimally selected which resulted in no performance degradation during the upgrade
Once the prepare activities were completed it was estimated that an additional 100 GB of storage was required to create the new tablespaces . With the help of the infrastructure teams we managed to get this provisioned within a short span of time so that it didn’t impact our overall upgrade runtime. The provisioning of this space was taken care much in advance when we performed the production upgrade.
The dev teams response was the key when we had several transports to be released and also to perform "modification adjustments" and they responded well and also gave resources in standby during weekends.
The technical upgrade was completed much ahead of time and the last hurdle in the way was a whole lot of configurations that need to be completed.
We started the solution manger configuration(Solman_setup) as part of which a whole gambit of checks and configurations were completed in over a 2 days period.
The Solution Manager Systems both the development and then the production a week later were released ahead of schedule with perfection and flawless execution
One of the key reason for the successful completion of the upgrade project was the ability to quickly learn from the development environment and transform the learning's in the production upgrade.
No Project work can be successful without support from the infrastructure teams and our infrastructure teams both storage and OS supported us exceedingly well.
The upgrade was very highly appreciated by the customer and was also discussed as a success story when they visited us .
Overall it was a great demonstration of how far team work can go ..