Technology Blogs by Members
Explore a vibrant mix of technical expertise, industry insights, and tech buzz in member blogs covering SAP products, technology, and events. Get in the mix!
cancel
Showing results for 
Search instead for 
Did you mean: 
former_member183519
Contributor
99,988

Dear All,

Recently i have a faced one issue where i required to change TR status from released to unreleased.

I have assumption that once we released TR(task) then we can not revert TR to modiable, but that was wrong.

SAP have provided program using which we can do this.

Initially TR was in Released status.

Step 1: Go to SE38-> enter program name : RDDIT076 -> execute

Step 2: Enter TR/Task which status you want to convert from released to modifiable -> execute program

Step 3: you will find TR with R (Released) status.

double click on R status(encircled in above screen), you will find below screen where need to edit R status to D status(D= Modified).

click on Save. -> exit from program

Step 4: go to Se01-> enter TR name, you will find TR in unreleased(modifiable) status.

Regards,

Hitesh

16 Comments
Labels in this area