on 2021 Jun 09 7:10 PM
Hello All,
i am confused with option (Swap planning status in material master- Advanced planning tab). Can anyone let me know the importance of this option in S4 HANA 2020 version.
and moreover, when you checkout the advanced planning check box once and save, then the system is not allowing you to uncheck in MM02. what is the reason?
Thanks,
Chandra.
swap planning status button is to change the planning status from active for planning to Marked for deactivation status.
Before removing the advanced planning check for a material, we may need to change the status as marked for deactivation and which will automatically sets deletion flag for the product in Advanced planning ( PPDS).
Then no planning will be done for that material either in advanced planning or in S/4 HANA MRP. Once we delete all dependent objects in advanced planning, system will allow us to remove the advanced planning check box.
No changes will get transferred to Advanced Planning after we set planning status as Marked for deactivation.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
10 | |
6 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.