on 2016 Oct 17 1:28 AM
Hi all
I have the following scenario. FInish goods and semifinish are planned in apo.
When I create a planned order in APO the semifinish good is ok in the components. But when I save and transfer to ECC, it is creating the planned order duplicating the semifinish good. It is adding a position 9999 at the end of the components with the semifinish good. And then it is transfer back to APO with the semifinish good duplicated.
The semi has X0.
Hello Carlos,
Please check the note below:
2307727 - Duplicate component during creation of planned order
I think that it will solve the issue.
Regards,
Yasmin.