on 2009 Mar 09 7:42 AM
Hi there,
How do I stop the system from trying to transfer the quality operation to APO. These operations are not set for scheduling or have any capacity allocations, therefore they always kick out errors.
Can anyone help pls.
Thanks
Robert
I don't know if that will help.
I want the integration model to stop wanting to transfer the particular operation to APO from R/3.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Robert,
Please refer the below link on procedure for deallocation of operation.
http://help.sap.com/saphelp_scm70/helpdata/EN/62/5286fb2ec711d3bf6c0000e83235ee/frameset.htm
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi there,
There is no scheduling formula in the scheduling tab.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Remove the scheduling formula from the resource assigned to quality operation.
Thanks,
nandha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
10 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.