Transfer Business volume total quantity in Business Volume Criteria

Pankaj_M
Participant
0 Kudos
187

In the case of Multi Payee Condition Contract (0S02), the requirement is to determine the scale for the settlement condition type based on the Total Business quantity for all the customers maintained in the Business volume criteria in the condition contract. However, the settlement calculation will be done on the basis of individual customer business volume quantity.

In this case, only the scales need to be determined based on the total business volume quantity.

In the business volume profile, the option to Transfer Business volume total quantity is available. How can we use this to transfer the total quantity for all the settlement documents and use this for scales determination?

Thanks and Regards,

Pankaj

View Entire Topic
gvictor
Active Participant
0 Kudos

Hi @Pankaj_M

You will need to use RBVT or RBVS condition type for the Business volume total or Business volume per split in your CCM pricing procedures, depending of your requirement, and assign the Subtotal 5. Adjust the Profile of Business volume accordingly with the RBVS or RBVT. 
Assign the scale routine 2 to your settlement condition or equivalent of RES1. 

 

Based on your version you may not have the scale routine 2, hence you will need to create your own custom scale routine. 

Regards, 