Hi All,

I am trying to use the Target Days of supply with PPDS.

The documentation says it works but on my tests

it does not.

IN SNP it does work.

Any ideas ?

Thanks,

T

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

The target days supply only works in PPDS with the SAP_PP_02 heuristic, or a copy of it. So check that first. Then check the target stock level method setting in the product master. It also influences the behavior of how the target days supply field is taken into account.

-Mike

liam_ryan2
Explorer
0 Kudos

Hi Mike,

I have setup the Target days supply settings in the material

master and I am using the planning of standard lots heuristic.

It works perfectly in SNP ... just not in PPDS.

Any other ideas ?

Thanks,

T