on 2024 Aug 12 12:04 AM
hi there
can anyone help me to find out when and who removed the operation from task list? there is an MP which has a task list attached; however the task list operation has been removed, therefore the MP which was supposed to be called on July 22nd, 2024 is on hold.
I added new operation on 08AUG2024 as shown in screenshot#1 and SAP generated new node and counter in table PLPO, can anyone tell me how I can find missing node 1 ?!
screenshot#1
then operation 20 has been deleted (as created in error) which updated deletion indicator in table PLAS in screenshot#2.
any thought, solution?!
#PLM Enterprise Asset Management (EAM)/Plant Maintenance (PM)
kind regards,
Mary
Hello @m_karimi ,
Did you try CDHDR and CDPOS table to check the changes in task list? These table has details of all changes in any transaction in SAP.
You can reschedule the maintenance plan and insert the operation in the order. This will solve the issue temporary.
Vaibhav Mishra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
13 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.