Subcontracting Purchase Order from ECC sent to APO creates a Plnd Order

Former Member
0 Kudos

Subcontracting Purchase Order from ECC sent to APO creates a Plnd Order with the same Purchase Order# in APO.

We want to influence the source of supply for this internally APO created planned order.

For this, I would like to know what user exit can be used, I have already looked at

(1) BADI: SOURCE DETERMINATION

(2) CIF INBOUND EXTERNAL PROCUREMENT on APO side.

Any other user exits or has someone worked on this scenario.

Thanks

Kumar

Accepted Solutions (1)

Accepted Solutions (1)

frank_horlacher
Contributor
0 Kudos

sources of supply for planned orders can be changed with the following BADI method:

Definition name /SAPAPO/RRP_SRC_EXIT

method RRP_USEX_SOURCE_FILTER

Answers (1)

Answers (1)

frank_horlacher
Contributor
0 Kudos

there is also BAdI /SAPAPO/PWB_SOS for a more general use to change the source of supply. the first one only applies to planned orders.