on 2011 Mar 03 5:13 PM
Hello Experts,
I have a scenario in which STR (Stock transport requisition) is FIXED pegged with Forecast and Sales Order.The requirement is, I want to fulfill sales order only with this STR not the forecast.
I am able to change the STR quantity with the pegged quantity with sales order using BAPI ( ie: STR Qty = Pegged Qty of SO) But when I see the pegging overview, in product view (/SAPAPO/RRP3),System is fulfilling forecast first and then sales order.
I tried to change the STR quantity manually in product view,but still it is pegged with forecast first which I dont want.
I want STR to be pegged only with Sales order not with any other order.
Do this require any setting somewhere in SPRO? or this is a normal case in SAP APO? or Do I need to break pegging relationship first then create new pegging relationship with SO only?
Please advice.
Regards,
Saurabh
You are right, you need to first break the pegging relationship and create a new pegging relationship with SO.
Which planning engine are you using in APO SNP
Regards
Kumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I think we can not break pegging and create new one with desired order.I am not using any SNP engine...
I have tried to change the STR qty but it is automatically respecting forecast first which i dont want to do....I changed order dates,Pegging Strategy in product master also but it is not happening......
I am talking about normal product view in which STR is fixed pegged with the SO and forecast,I want to change STR qty in such a manner that it should fulfill only pegged sales order not any other order.
Please advise me how to achieve this without any planning run?
Regards,
saurabh
User | Count |
---|---|
8 | |
6 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.