Should we take the backup of IBP Test & IBP Production System if we need to update the Time profile

saranya4
Newcomer
0 Kudos
94

Hi Team,

For an IBP Template Pivot table issue, SAP has suggested to correct the Time profile description and upload the time profile to IBP system.

later should we activate the planning area or it is automated?

Thanks in advance,

saranya

 

View Entire Topic
dlellou
Explorer
0 Kudos

Saranya,

Changing time profile is a touchy task, following cases may apply

1- you want extending periods in future or/and remove past ones. This is easy, you need to create the new periods with new periodIDs, and leave unchanged the periodID of periods you keep. The ones you delete will simply disappear if they are not in the uploaded and changed timeprofile. May have to run a purge job I think

2- You want to redefine the Start and End date of existing periods. Don't do you will lose all data for sure. 

3- You simply want to change labels or period weight factors or any associated attributes of periods, just do. Think that your disag logic could be impacted by that and you may need to rebalance some disag from scratch

Anyway for case  and  2 and 3 I would backup, or discuss with SAP as they perform backup checkpoint regularly.

And because SAP is SAP, make a mini test on a separate area just to be sure

 

Cheers, Daniel