SAP DM - How to create routing(or operation activity) which doesn't depend on Order

okakoshow
Explorer
0 Kudos
146

Hi experts,

When I integrate production order from S/4 HANA to DM,

operation activities are created with order no. (operation activity sample below : order no is 1001597)

okakoshow_0-1731552006353.png

That means, even if I use same material, each order has different operation activities.

Could anyone tell me how to fix that.

Best,

KoichiOkamoto

 

View Entire Topic
sanjeev3009
Associate
Associate
0 Kudos

Hello ,

You can define the ME Operation name for ach step of the routing in the master routing using tcode CA02. Please refer below screenshot. This will prevent the order download interface to create order specific operation name wverytime when you download a new order. 

sanjeev3009_0-1731563266594.png

 

Regards,

Sanjeev Sharma

 

 

okakoshow
Explorer
0 Kudos
Thank you very much!