3 weeks ago
Hi experts,
When I integrate production order from S/4 HANA to DM,
operation activities are created with order no. (operation activity sample below : order no is 1001597)
That means, even if I use same material, each order has different operation activities.
Could anyone tell me how to fix that.
Best,
KoichiOkamoto
Request clarification before answering.
Hello ,
You can define the ME Operation name for ach step of the routing in the master routing using tcode CA02. Please refer below screenshot. This will prevent the order download interface to create order specific operation name wverytime when you download a new order.
Regards,
Sanjeev Sharma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.