Return the System Status from ORAP (Order Approved) to ORAI (Order Approval In Process)

aoime02
Discoverer
0 Kudos
207

Is it possible to return the System Status from ORAP (Order Approved) to ORAI (Order Approval In Process) in the Configuring of Phase Control Codes under the Adjust System Status setting?

View Entire Topic
vijayalaxmimelavanki
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello,

Can I know the business need to revert status to ORAI from ORAP?

Phase control codes can be configured in such a way that it will be set on an entity when the entity reaches a phase or subphase or used to block the entity attaining a particular phase or subphase.

For more information, please refer to below help documents.

Phase Control Codes | SAP Help Portal

Configuring Phase Control Codes | SAP Help Portal

Please refer below blog for configuration of phase control code with example.

Phase control codes for Maintenance Orders in SAP ... - SAP Community

Hope this helps.

BR,

Vijayalaxmi Melavanki

aoime02
Discoverer
0 Kudos

Hi Vijayalaxmi Melavanki,
Thank you for your response.

The business needs the maintenance order to have it re-approved once there is an additional unplanned material consumption either via reservation and/or purchase requisition.

This scenario always happening in the actual maintenance activities.

Therefore, it is suitable that a maintenance order will be undergo re-approval once cost incurred will be changed especially when the cost added is significant value which need to be approved with several level of approval based on the workflow scenarios for maintenance order approval.

As for phase control code configuration, is it possible to adjust the system status in that way stated above? Or my idea is setting the phase control code to set a certain system status for example (Locked) once the order is set to Work Started to prevent the trades person to add materials and they can add only once the control code is being deactivate by an authorized role.

Regards,

Alvin Infante-

vijayalaxmimelavanki
Product and Topic Expert
Product and Topic Expert
0 Kudos
Hello Alvin, with the current version of SAP S/4HANA Cloud,public edition the cost approval workflow for maintenance orders is only available at the approval phase as you know. With the phase control settings ,even after the order is approved you can still activate the approved phase and block the preparation phase so that order cannot be released yet. This is one way you can have a check on unplanned components which can be reviewed before the order is released for next step. Alternatively, you can check for reports (either standard or custom) which can give a view on new components added contributing to huge, planned costs. Hope this helps.