on 2007 Jun 25 1:20 PM
Hi All,
Is there anyone who has used REM Heuristics (SAP_REM_001 or SAP_REM_002). How can we make system to use Rate/Quantity based capacity definitions? Is it possible to define daily capacity of line resource in terms of quantity of the product, if we do not use Model Mix Planning?
Thanks,
<b><i>Ergul</i></b>
This link only display header information for APO...
But I have not found a way to do this via R/3 CIF.
In APO you can define a resource to be quantity based vs time based.
But you can't create a work center in R/3 that is quantity based.
If anyone knows a way of doing this, let us know.
Ken Snyder
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Ergul,
It is possible to define daily capacity of the line resource in terms of Quantity of product....
You can adopt it by creating the rate routing in R/3 and maintianing the same in the Production versions in the column Rate based planning. and transferring same as ppm in APO for further planning.
Just have a look on the REM_ HEURISTIC help from link provided
http://help.sap.com/saphelp_apo/helpdata/en/7e/63fc37004d0a1ee10000009b38f8cf/frameset.htm
regards
Kiran
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
11 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.