cancel
Showing results for 
Search instead for 
Did you mean: 

PurRqs will be generated when Available Qty -1000 always

Anusorn_P
Discoverer
0 Kudos
275

Dear All,

Can someone help me to fix this issue? I want to purchase a raw material to be ready before using. I don't want the Available Qty to be minus(-). I had checked in MRP setting, but I cannot see any issue. Please help me.Screenshot 2024-09-18 094854.jpg

Stocki
Explorer
0 Kudos
Hi. Is planning done in ECC/S4 or PPDS?
View Entire Topic
Anusorn_P
Discoverer
0 Kudos

stock.jpg

Hi Stocki. Here is Plant Stock of this material. I cannot see any pending on quality status.

Stocki
Explorer
0 Kudos
Ok. So I do not see the reason why MRP is doing it like this then. For some reason it thinks it has 1000 available which are not there, but I have no clue where this may come from. Sorry.
Stocki
Explorer
0 Kudos
One last idea - is there any discontinuation information in MRP 4. If there is - that could be another rootcause. If not, I will not be able to help.