cancel
Showing results for 
Search instead for 
Did you mean: 

PurRqs will be generated when Available Qty -1000 always

Anusorn_P
Discoverer
0 Kudos
279

Dear All,

Can someone help me to fix this issue? I want to purchase a raw material to be ready before using. I don't want the Available Qty to be minus(-). I had checked in MRP setting, but I cannot see any issue. Please help me.Screenshot 2024-09-18 094854.jpg

Stocki
Explorer
0 Kudos
Hi. Is planning done in ECC/S4 or PPDS?
View Entire Topic
Anusorn_P
Discoverer
0 Kudos

MRP1.jpgMRP2.jpg

Here are MRP1 and MRP2 tap.

Stocki
Explorer
0 Kudos
Hmm. Don´t see a reason yet... is there inventory available on this material? Is there something in quality status maybe that is not shown in MD04, but taken into account by MRP for its calculations?