cancel
Showing results for 
Search instead for 
Did you mean: 

PurRqs will be generated when Available Qty -1000 always

Anusorn_P
Discoverer
0 Kudos
283

Dear All,

Can someone help me to fix this issue? I want to purchase a raw material to be ready before using. I don't want the Available Qty to be minus(-). I had checked in MRP setting, but I cannot see any issue. Please help me.Screenshot 2024-09-18 094854.jpg

Stocki
Explorer
0 Kudos
Hi. Is planning done in ECC/S4 or PPDS?
View Entire Topic
Anusorn_P
Discoverer
0 Kudos

ECC, sir.

Stocki
Explorer
0 Kudos
please also share MRP 1 and MRP2 tabs from Material master