Dear All,

Can someone help me to fix this issue? I want to purchase a raw material to be ready before using. I don't want the Available Qty to be minus(-). I had checked in MRP setting, but I cannot see any issue. Please help me.Screenshot 2024-09-18 094854.jpg

Stocki
Explorer
0 Kudos
Hi. Is planning done in ECC/S4 or PPDS?

Accepted Solutions (0)

Answers (3)

Answers (3)

Anusorn_P
Discoverer
0 Kudos

stock.jpg

Hi Stocki. Here is Plant Stock of this material. I cannot see any pending on quality status.

Stocki
Explorer
0 Kudos
Ok. So I do not see the reason why MRP is doing it like this then. For some reason it thinks it has 1000 available which are not there, but I have no clue where this may come from. Sorry.
Stocki
Explorer
0 Kudos
One last idea - is there any discontinuation information in MRP 4. If there is - that could be another rootcause. If not, I will not be able to help.
Anusorn_P
Discoverer
0 Kudos

MRP1.jpgMRP2.jpg

Here are MRP1 and MRP2 tap.

Stocki
Explorer
0 Kudos
Hmm. Don´t see a reason yet... is there inventory available on this material? Is there something in quality status maybe that is not shown in MD04, but taken into account by MRP for its calculations?
Anusorn_P
Discoverer
0 Kudos

ECC, sir.

Stocki
Explorer
0 Kudos