Hi All,
my scenario is:
the product can be produced in resource A resource B and resource C, the production times are different so I have created 3 production versions. The customer's request is to start from resource A, if he is busy I choose B then C. I'm doing tests in PP / DS (SAP HANA), do you have any advice on how to proceed?
Thanks so much
Request clarification before answering.
Just use the procurement priority option, where A resource related prodtion version / PDS should have the value 1 followed by 2 & 3 in B & C respectively