Hi Experts,

I have created a planned order for the FG item and set the conversion indicator on RRP3 view . The planned order got converted in APO and ECC as process order but the process order number which has generated in the ECC not updated in PPDS.

we have maintained all the necessary settings as per the PP/DS Cookbook for S/4HANA 1709/1809

when I have ran the CCR i got the error code 166 but it could not succeed even though order push to APO button .

Can you please advise ?

Thanks

Sreedhar

0 Kudos

screenshot CCR

View Entire Topic
former_member747603
Discoverer
0 Kudos

Hi Sreedhar

Make sure if you have maintained the number ranges in S4 Advance planning

Check your SPRO setting->Advanced planning->Global Setting->Maintain Number Ranges for Orders.

Please Maintain it and then check out below option as well.

SPRO->Advanced planning->Global Setting->Maintain Global Parameters and Defaults-> Use Number Ranges(Check this option).

Thanks,

Chandra.

Enda
Product and Topic Expert
Product and Topic Expert
0 Kudos

Welcome and thanks for visiting SAP Community to get answers to your questions. Check out our tutorial to get started in SAP Community: https://developers.sap.com/tutorials/community-start.html By adding a picture to your profile you encourage readers to respond to your question. Learn more about your profile here: https://developers.sap.com/tutorials/community-profile.html