on 2011 Jun 20 1:59 PM
Dear all,
We have done all settings for POD confirmation as specified in S55 Contract Manufacturing. But when we are posting the GR from VL32N for the delivery, the output message is not getting populate automatically.
We are able to post by manually populating the message, post the GR and the same the is getting updated in SNC.
Request to please let us know if we are missing something.
thanks,
mahesh.
Hi Mahesh,
As per CM documentation you must be having OPOD output type.
To automate GR transfer you need to below settings.
Go to transaction code NACE in ECC and then select E1 (Inbound Delivery).
Now click on condition records button select OPOD output type and enter delivery type as EL(Shipping Notificat.).
Press F8 and enter as:
Delivery type=EL
Function:LS
Partner:<Logical system>
Meduim:6
Date/Time:4
Lang:EN
and save this setting.
This will send GR automatically whenever inbound delivery is created.
Regards,
Nikhil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mahesh,
Yes you are right it should come.
But have you maintained NACe settings?
If this setting is maintained then create inbound delivery and check whether OPOD output is tirggered or not.
Also check OPOD output type setting.
Tcode:NACE
Select E1 and click on Output types and select output type OPOD.
Now click on details(CtrlshiftF2)
Check default values tab:
Dispatch time: Send immediately
Transmission meduim:EDI
Regards,
Nikhil
User | Count |
---|---|
11 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.