Hi experts

I can run Planned Replenishment with the old material and system can created the warehouse task. but for the new product created today, after excuted the REPL program and it shows the related replenishment quantities, but when click "perform replenishment"  system alway says "Replenishment run started in whse no. W202 with replenishment strategy Planned Replenishment. Message no. /SCWM/REPL008". I have compared the product parameters and they are same, some backgroud as below:

1, I use the consign stock for vendor,

2, have assigned the fix bins to the new material.

  please advise.

Leo

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

I have get the answer from SAP, notes 1784164 can solve this problem.

the Symptom is "If stock determination is active for such a batch product and no batch is specified in the delivery, the system may not find any stocks even though stocks do exist"