Hi folks,

i need some clarification/suggestions from you regarding T-Code MD07 output.

While checking Output of the MD07 T-code by MRP Controller wise it gives the outputs (screenshots below for reference)

MRP Controller-01 = 2 Material

MRP Controller-02 = 219 Material

MD07-cntrlr 1.pngMD07-cntrlr 2.png

but checking with over all plant level without giving any MRP Controller information it shows very limited data (screenshots below for reference).

Overall Plant level without specifying MRP Controller = 8 Materials only

MD07-no cntrlr.png

i need all MRP Controllers material details by giving Plant alone in MD07 tcode.

(Example : Only giving as Plant input, Plant contains total two MRP Cntlr --> MRP Cntlr 01 + MRP Cntlr 02 = 2 + 219 = 221 materials )

Is it possible to get this total Output from MD07 T-Code or from any other Standard T-Code ??

kindly give your inputs on this. 

Thanks in advance, 

Regards

Aravind

 

 

 

 

View Entire Topic
MohdRashid
Active Contributor
0 Kudos

Hi 

Please tell us what are the additional information you are getting in Plant by executing MD07. When I executed I noticed only MRP Controller field in MD07. I used ECC for this test.

Also it is not relevent but more details 

https://community.sap.com/t5/enterprise-resource-planning-blogs-by-members/md07-mrp-exception-monito...

https://community.sap.com/t5/enterprise-resource-planning-blogs-by-members/comparing-md07-md04-vs-mo...

Regards

Rashid 

 

aravind_rr
Participant
0 Kudos
Hi Rashid - thanks for your links. i am including the images for question clarification with details