on 2024 Jun 13 5:18 AM
Hi Suresh,
Thank you for your question. The Regenerative Planning checkbox is always selected automatically, to make sure that all materials are included in the MRP run. This is a default setting in S/4HANA Cloud and cannot be changed. The checkbox itself is only displayed for information purposes, so that material planners are aware of how the MRP run is performed. We will improve the documentation for the checkbox to include this information.
Best
Antje
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.