on 2023 Jan 30 9:20 AM
Hi All,
Manufactuing order crate released, and staging is done. BOM materials are staged in the PSA locations. Once the production process done while posting goods receipt for the production order material document is generating instead of inbound delivery.
I think I am missing some configuration could you please help me in this.
c ehck the configuration.
Regards,
Chand
Do you maybe have synchronous posting activated on the production profile (in case you use embedded EWM)? Then you have no inbound delivery
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Son,
Thank you very much. I just saw that in SAP Blog and understand that it is activated in the below path.
In Customizing for Production under Shop Floor Control Master Data Define Production Scheduling Profile, you have set the Post Synchronously to Bin field to a value other than Never
I think we don't have inbound delivery for the Production order in the S/4 HANA 2021 because it gives provision to post directly.
Please correct me if I am wrong.
Communication of Goods Movements from Production | SAP Help Portal
Thanks once again.
regards,
Chand Basha.S