a month ago
I have two storage location MRP areas. one for the Production storage location and the other for the Sales storage location.
For sales orders, I will pick stock only from the sales storage location.
But for production orders, I will pick stock from both sales and production storage locations. (Currently, If I give the requirements at the plant MRP area, it's getting passed to the Storage location MRP area based on the Production storage location)
Is there any way to do this on standard MRP?
If yes how are the requirements for the sales order and Production orders to be maintained and how is the MRP to be executed? At plant MRP area or at Sloc MRP area.
Header material
Component material
Request clarification before answering.
Hello @RaghavanKathamuthu
MRP areas by definition are planned separately. Therefore you can not have them separated from sales orders point of view and combined from production order perspective.
What you can do however is implement Stock Determination in production orders and customize the strategy so production storage location is picked first and if stock is not available there, then sales storage location is picked next.
Stock determination is customized in Materials Management -> Inventory Management and Physical Inventory -> Stock Determination -> ...
Best regards
Dominik Tylczynski
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.