Hi,

we are migrating (with DMO) our SCM (APO) system with external liveCache (SapDB) to HANA with integrated liveCache.

After SUM stops in phase "Restore liveCache" we run program /SAPAPO/OM_LC_DOWNLOAD_UPLOAD and executed steps "Load Master Data" and "UploadliveCache Data" without errors.

After performing step 6. "Compare liveCache with Download" (in Section C) we get a lot of ( about 3.000) warnings in protocol (see also attached file):

(...)

Produktionsauftrag BO2922 (Eigenf.): Dates/times changed by up to 82801 seconds

Produktionsauftrag BO2330 (Eigenf.): Dates/times changed by up to 54000 seconds

Produktionsauftrag BO1865 (Eigenf.): Dates/times changed by up to 32400 seconds

(..)

Why is there such a big gap between liveCache and download?

Kind regards

Stefan

View Entire Topic
former_member229109
Active Contributor
0 Kudos

Hello Stefan,

- Check if you applied all recommended notes before you run the download on the source system and upload on the target system.

- Check if you updated the timelines and calendars for the resources before you run the download.

- Create the SAP message to the component BC-DB-LCA for further analysis of the case on your system by SAP support.