Hi

I would like to understand the practical application of the option - 're-assignment of order confirmation' functionality in EDQA process in GATP ?

As per definition it is ----

"During this process the event-driven quantity assignment (EDQA) executes a reassignment of order confirmations (ROC) in order, for example, to assign confirmed quantities from items with a low priority to items with a high priority"

If that is the case then where does orders with 'high' priority which are not confirmed in the first place (i.e. at the time of sales order creation) come into picture in this process ? Other way round, what is the purpose of processing only the confirmed orders together leaving unconfirmed orders (may be with high priority) aside ?

So in which business case this option of ROC is applicable ?

Also, does ROC update the re-assigned confirmations back in ECC Sales Orders and when ?

Regards,

YR

View Entire Topic
Dhaivakumar
Explorer
0 Kudos

Hi YR

We are using extensively ROC functionality for our business requirement.

We are using 2 order types , one for stock order and another one for Emergency order type  and we have activated ROC for emergency order type rule .example I have stock 10 qty , initially stock assign to the stock order and confirmed.Before check and combine( outbound delivery creation ),if we receive a emergency order , during gATP check system will reassign stock from stock order to emergency order and stock order  will become a backorder.

second scenario

EDQA will trigger based on stock changes ( inbound delivery, sales order cancel..etc.) if you have emergency order as Backorder , if any stock changes system will check the stock and confirmed orders , qty will  reassign to emergency order.

Please let me know if you have question .

former_member566355
Participant
0 Kudos

Hi Dhaivakumar/Babu ,

In line with Babu's explainations, I would like to point out that I do not see the any entry in /SAPAPO/EDQA.

Can you please help me out in here ?

YR

babu_kilari4
Active Contributor
0 Kudos

Hello YR,

If you do not see an entry in /SAPAPO/EDQA transaction, the only possible reason that I could think of is that there would be an error with WF settings or ROC Config in your system. Did you setup the necessary ODLs properly and triggered the ROC with the correct event ?


Were you also able to see the ROC confirmation picture when you did the ATP check in online mode.

Once you check all these things, you may get a clue. Unfortunately, as I do not know how your system has been setup I may not be able to point to the exact cause.

Hope this explanation helps.

Babu Kilari

SCM APO Consultant

former_member566355
Participant
0 Kudos

Hi Babu,

In  /SAPAPO/EDQA_OS (EDQA simulation) the message is ....Process Is Not Active (status display)

In transaction SWETYPV, linkage in active

Also in transaction /SAPAPO/EDQA_EC I checked that the linkage is active.

What am I missing in this entire process ?

YR

babu_kilari4
Active Contributor
0 Kudos

Hello YR,

Please revisit the configuration in /SAPAPO/EDQA_PD transaction as well and make sure that the process category relevant settings are configured as expected.

Babu Kilari