on 2016 Jun 03 6:20 PM
Hello All,
I've an issue where CTM has to consider the Weekly Capacity, under the Special Strategies in the CTM profile - We defined "Use Setting from Resource".
In the resource master, capacity is set up for each day so when CTM is executed my assumption is that it is only considering the capacity for each day.
CTM Time stream is defined for Weeks.
How do I configure the Weekly capacity in the resource master?
In the Resource Master >> under SNP bucket capacity I selected the option 'X Maintain' but in the Period Type it has option only to enter Day.
I selected Day in the period type, 7 days in Number of Periods to see if CTM considers the capacity for whole 7 day period but it still looks at only each day's capacity while Planning.
Issue Background:
Requirement:
Since Manual Planned Orders are already consuming excess % of resource Capacity on a specific day, CTM when executed should consider the total capacity for the week and accordingly generate orders in the other days of the bucket without causing any overload
Kindly suggest .
CTM is daily planning. If users are manually entering planning books then that is SNP Heuristics.
CTM can not consider weekly capacity. It is using daily buckets, that is sole definition of CTM.
Search for the exact same question someone else asked just last week.
Ken
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
5 | |
4 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.