Can I constrain production for a group of products on another time level?

abarofsoap
Explorer
0 Kudos
472

Using IBP R/S Time Series Optimizer. (Currently using v2311)
Is there a way to constrain production for a group of products on another time profile level that the optimizer uses?

Ex.
Optimizer runs on daily buckets. The constraint should be stored in calendar weekly buckets.
Product A, B and C runs on several parallel production lines.
IBP should in total only produce max 100pcs per calendar week for both Product A and B.
IBP should in total only produce max 100pcs per calendar week for both Product B and C.
(Note that B belongs to two constraints)

I don't care on what day these 100 are being used and I don't want to dis-aggregate the constraints to daily level.

View Entire Topic
abarofsoap
Explorer
0 Kudos

I need it to work with 'Time Series' based planning and cannot see how 'Settings for Order based planning' can help with that.
But if there is a solution in there it probably would have meant to change time time level for 'CAPASUPPLY' to weekly,
I still want to keep CAPASUPPLY on a daily level for all other resources,

Any other suggestions?

guglanigaurav1987
Product and Topic Expert
Product and Topic Expert

Have you explored 'Aggregated Constraints' functionality in Time Series Optimizer?

key Figure 'Max Aggregated Production Capacity Usage'.

https://help.sap.com/docs/SAP_INTEGRATED_BUSINESS_PLANNING/feae3cea3cc549aaa9d9de7d363a83e6/a57774a7...

abarofsoap
Explorer
0 Kudos

Yes, thanks!
This was probably the solution I was looking for, even though Aggregated Constraints is a bit cumbersome to work with.

I also enabled "Use cost key figures for minimum/maximum violations of aggregated constraints for Production Receipts" to make it a bit softer.