on 2018 Jun 20 10:38 PM
Hello All.
We using block planning in PPDS and the orders planned and scheduled at block limits. So, we see the Avail date in RRP3 for Receipts and Requirements for that orders are in line with Block end date and Block start date.
But these dates are not in line with Basic start and Basic end date in ECC? Scheduled start and end date are in synch with the order activity start and end date.
My question is:
How and where do we see the Block start and end date in ECC order?
Is this standard behavior of the system for block planning?
Thanks in advance for your input
Kumar
Request clarification before answering.
Kumar,
1) the dates you see in APO are the scheduling dates, not the basic dates.
2) i don't think you can see block planning data in ECC (but not sure in 100%)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
5 | |
4 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.