cancel
Showing results for 
Search instead for 
Did you mean: 

Which PO's are/not supported in MM-SUS ?

Former Member
0 Kudos

Hi ,

We are going for SRM 7.0 with ECC 6.0 (Ehp4) and MM-SUS scenarion .

Can any one please confirm me , along with Standard PO , Account assignmnet catagory (standarized the solution for Service PO for SRM 7.0 with ECC 6.0 (Ehp4) ,as per note 868192 ) ,which PO ( I mean ...Consignmnet , Limit/Blanket, Subcontracting..etc) are supported / not supported in MM-SUS scenarion ?

Thnaks in advance

Regards

NAP

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Narendar

Standard, Limit/Blanket, Service, Consignment POs are supported as standard.

In my understanding Subcontracting PO can also be sent but Subcontracting process like Goods delivery, processing of components to make final products will not be supported in SUS....

Regards

Virender Singh

Former Member
0 Kudos

Thanks Virender,

Can we identify the different Item catagory in the PO in SUS (in MM-SUS) ?

In case Material PO , there is ASN done in SUS and I/B Delivery & GR in MM ,then how we treat Service PO in SUS i.e. what is about ASN,I/B Delivery and Serviec Entry Sheet in MM-SUS scenarion?

Can you/ anyone please suggest on this ?

Former Member
0 Kudos

Hi

There is no I/B in Service Scenarios. It's only Service entry sheet & Invoice.

Regards,

NNK

Former Member
0 Kudos

Great . Thanks Nitin.

In case of Meterial PO , can we , by removeing /deactivating the functionality of " the ASN in SUS and I/B Delivery and GR in ECC " do directly GR ( Confirmation) in SUS ? Is it posible ? If yes ,how ?

Since ASN and I/B delivery seems unnecssary /extra steps for MM-SUS scenarion.

Regards

NAP

Former Member
0 Kudos

Hi Narendra

You can avoid ASN in SUS by selecting appropriate Confirmation Control Key in ECC PO Document type. You dont need any development or configuration in SUS ofr that

IN that case you can complete GR in SUS which will create a Goods movement in ECC...

Regards

VirenderSingh

Former Member
0 Kudos

Great Thanks Viru !

Cleared . It'll avoid unnecassry steps in SUS. Resolved.

Former Member
0 Kudos

Good Luck Narendra

You are on your way to a good system implementation!!!!!!!!!!

Regards

Virender Singh

Answers (0)