Dear SAP gurus,
We are using SRM 7 with EHP1 and ECC 6 as backend. We are using plan driven procurement, but as we're not using XI/PI we're using program BBP_EXTREQ to transfer PR from ECC to SRM.
When the PR comes to SRM as SC, the source indicator is 'X', which is correct, as we can now do sourcing. We click propose source of supply, found contract, and the proceed to create PO.
Now when we come back to sourcing cockpit we still find the same SC sitting there. Checking in SRM, we find out that the source indicator is still 'X'. As per what I read from other post, it seems that there is field BBP-PDIGP-QUAN_PO_E which should be filled with PO qty, in this case the quantity is still 0 though the PO already created. (note that we schedule BBP_GET_STATUS2 and clean_req_requp per 2 minutes already).
This is confusing as we ONLY have this behaviour in our production system, but it works perfectly well in our QA system (source indicator changed to blank and QUAN_PO_E is filled).
Can someone shed some light on this?
Best regards,
John
Hello,
Kindly refer to the SAP note 1432540 ( Sourcing relevant flag is not updated properly) to resolve your issue here.
Best Regards,
Rahul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
In order to eliminate if issue lies in the variant used for BBP_GET_STATUS2, you can execute this program manually and enter the cart number directly. Just to check if issue does not lie in variant.
Regards,
Ricardo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.