Please also check this whether it is working

 

To skip a budget check, the parameter Application.Budget.ReqSubmitOnError needs to be enabled and the below-mentioned steps have to be followed:

  1. Edit the requisition.
  2. Access the Budget Details link under Cart Summary.
  3. Select Action > Skip Budget located in the lower right corner.
  4. Click Save.

Now, you can approve the requisition. These actions only skip the budget check for that particular requisition; it does not affect your site's budget code allocation. You must act as or be a member of the Budget Approver group to take these actions.