Plan driven procurement PO

Former Member
0 Kudos
87

We are using the classic scenario with plan driven procurement. The issue is that we are unable to change the direct material PO created in R/3. We receive the following message

(ME888 - BBP purchase order cannot be changed in R/3 system (Display only)

Is this standard ? How can one change the direct material POs then ?

Thanks

-Bakulesh

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

I think you are in Extended classic scenario.

Check once again, the PO created in SRM cannot be changed in R3, it will be for display purpose only.

Regards

Reddy

Former Member
0 Kudos

I think the reason is that the buyer is assigned to a local pur org in SRM. Do we have create a local buyer or a "R/3" buyer ?

Former Member
0 Kudos

Hi

The buyer should be assigned to backend purchasing org in case of classic, I suppose...

Regards

Reddy

Former Member
0 Kudos

Reddy:

I assigned a backend pur grp to the buyer in the org plan, but the requisitions are showing up in the local buyer's sourcing cockpit. Don't know why ?

-Bakulesh