Hello All,

We are into SRM 7.0 classic scenario, we are using backend system as ECC 6.0 EHP 4.0 and currently in SRM system the backend system type is maintained as ERP_3.0 due to which some issues like contract mangament services are created in backend system. we have consulted SAP and they are suggesting to use ERP_4.0, if we directly change the system type in all the system, is there any impact in SRM side and ECC side. please let me know.

Thanks

Santhosh Kumar G

View Entire Topic
Former Member
0 Kudos

Hello Santosh,

there are 2 case for system configuration

backend system as ECC 6.0 EHP 4.0 than Document Like PR , PO , confirmation and contract will get created by Xml interface for this you need to activate configuration of E SOA. which may or may not need PI depend on ECC system support pack level.

if you are making backend system as ERP_3.0, These will be no impact and  The PR/PO will created by RFC and Confirmation will be created By Idoc interface.

We have done second setting for one of out rollout.