Error message in SLG1 - No address found for partner function type Ship-To

Former Member
0 Kudos

Hi All,

We are using the plan driven procurement scenario to transfer MRP generated requisitions to SRM 5.0 (extended classic scenario).

The requisition that is transferred through the EXTREQ program fails on its way to SRM.

The error message we see in the outbound queue (SMQ1) from R/3 is "Application aborted due to serious problems" with the status - ANORETRY.

On the SRM side, the SLG1 log shows a hard stop error with the message " No address found for partner function type Ship-To Address" Message no. BBP_PD051

System status INCM is active (Shopping Cart 1000000053) Message no. BS013

The ship to address attribute is already maintained in the org structure.

The configuration for MRP channels is complete and assignment of responsibility to the Purchase group is in place

Has anybody encountered this issue ?? Seeking your help.

Thanks,

Pai

View Entire Topic
Former Member
0 Kudos

Check if your RFC user being used for PDP is in the org. model in SRM.

Former Member
0 Kudos

Yes.. It is assigned in the org structure as part of the MRP channel customisation

former_member183819
Active Contributor
0 Kudos

Hi

paste the smq1 full message here

do you have account assignment in your PR?

in smq1 do you get message ext. requirement can not be created

br

muthu

Former Member
0 Kudos

Hi,

We are on SAPKIBKT13 (SRM 5.0). The OSS note 1101215 is already in the system.

Here's the full message in SMQ1

Function : BBP_BC_EXTREQ_INB

F-Number : 00000001

RFC-Type : qRFC with Send Queue (OUT-Queue)

Return Data:

IF-Function:

Status : ANORETRY

TYPE : A

ID : BBP_EXTREQ

NUMBER : 013

MESSAGE : Ext. requirement cannot be created, see application log f

LOG_NO :

LOG_MSG_NO: 000000

MESSAGE_V1:

MESSAGE_V2: BBP_EXTREQ

MESSAGE_V3:

MESSAGE_V4:

PARAMETER :

ROW : 0

FIELD :

SYSTEM :

The PR is not account assigned. It is a standard PR generated by MRP

Edited by: Prashanth Pai on Jun 3, 2009 8:16 AM

former_member183819
Active Contributor
0 Kudos

Hi prasant

it is a limiatation of SAP SRM on direct material.

please create oss message and update us reply here .

good luck.

br

muthu

Former Member
0 Kudos

Is your issue resolved? We are also facing same error and we are on SRM70.

Thanks,

Jagadish

JaviSimón
Explorer
0 Kudos

Hello,

For if it helps someone:

I had the same incidence, extact.

The problem was the organizational model (PMOMA_BBP) for the RFC user, specifically the company was not informed.

Regards

Former Member
0 Kudos

Hi,

The Delivery address in the PR in ECC is not complete in order to create the shopping cart.Edit the PR and Provide all the necessary fields in PR delivery address (for eg name1,2, PIN code, region, country etc.. ). Then transfer the PR again.

regards,

MRao

former_member206968
Active Contributor
0 Kudos

Hi,

For Direct material PR transfer to SRM, Please ensure that purchasing group has a buyer user id assigned under it and also 'Ship to' attribute is maintained for the buyer. Also attribute dp_proc_ty should be maintained for purchasing group and plant/storage locations need to be assigned correctly.

Regards,

Sanjeev