CIG mapping for planned delivery cost

uyentnh789
Explorer
0 Kudos
568

Hello everyone,

I included additional pricing details onto PO and mapped them at item level as guided in CIG custom mapping tool. Below is the reference link:

https://ga.support.sap.com/dtp/viewer/index.html#/tree/2873/actions/41970:41971:42051

When I posted invoice in DSN, the freight cost (FRB1) is calculated in invoice summary as total charges BUT not as Shipping amount

When i summitted the invoice and sent to S4, this charge was not included in the Idoc. Hence, I had to do a custom mapping to map this to E1EDK05 as below detail:


Charge was included in the Idoc. However, It cannt be read in S4 and had error:


My question is:
1. Do i have to map additional pricing details onto PO at both level: header and item?

2. Why there is no standard available mapping for this cost in CIG and we had to map it manually?
And did i map the total charges to E1EDK05 correct? or the charges should be mapped at item to E1EDP05 ?

3. have any one faced the same issue and had resolved it? Could you help to share?

Thank you!

View Entire Topic
Prem_Tracz
Product and Topic Expert
Product and Topic Expert
0 Kudos

Planned delivery cost is not supported for EDI invoices.

Therefore this will also not work in DSN that is basing its integration on that functionality. See more info [ 2567788 - EDI: Delivery/Freight Costs are not considered during Invoice creation via IDOC ]

Unplanned delivery cost field will have to be utilised for your use case.