Hello,

Is there a way that when creating a SC item the systems checks if the delivery date is a working day on plant calendar in backend system and if not give an error message?

Regards,

Nelson

Accepted Solutions (1)

Accepted Solutions (1)

yann_bouillut
Active Contributor
0 Kudos

Hi,

Yes with implementation of BBP_DOC_CHECK badi

Kind regards,

Yann

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

You can maintain the same calendar in SRM also,path is:

SAP Web Application Server>General Settings>Maintain Calendar.

BR,

Disha.