Hi Experts,
Please I have a question I'm not sure When the planner checks the capacity load of a work center, which data of the order is used?
1-Duration of the activity
2- Scheduled start
3- Basic start
4- Amount of work
Thank you,
Regards,
Request clarification before answering.
Hello Peter:
Capacity load transactions (like CM01) takes into account:
2- Early start of the operation: to determine the week were the order is considered in the load
4- Amount of work: to compare against the capacity of your work center
Hope this helps with your inquiry.
Have a nice day,
Jimena