Work center Load

YBS
Participant
0 Kudos
512

Hi Experts,

Please I have a question I'm not sure When the planner checks the capacity load of a work center, which data of the order is used?

1-Duration of the activity

2- Scheduled start

3- Basic start

4- Amount of work

Thank you,

Regards,

View Entire Topic
0011693591
Discoverer
0 Kudos

Hello Peter:

Capacity load transactions (like CM01) takes into account:

2- Early start of the operation: to determine the week were the order is considered in the load

4- Amount of work: to compare against the capacity of your work center

Hope this helps with your inquiry.

Have a nice day,

Jimena

YBS
Participant
0 Kudos

Thank you for your help