Settings for Assign Roles to tasks and vice-versa in PPM Template

ashwinipingle
Participant
0 Kudos
941

Hi PPM Experts,

I am setting up a Project Template in PPM 5.0.

In each of the phase and task, I assigned a Role to a Task in the Responsible Resource field. This is in structure view.

What I expect is -- as I navigate to the Resources view --> Details --> Tasks tab, the Task should appear here automatically, since the Responsible Role is already set for each Task. However I find that I have to again assign Task to the Role in the Resource view.

Can someone explain what should be the right system behaviour. My expectation is that if you set the Role in task screen, it should appear in the Resouce-->Detail-->Task screen and vice-versa. Currently I need to do the settings in both the screens. Why?

Best Regards,

Ashwini Pingle

View Entire Topic
judith_gabriel
Product and Topic Expert
Product and Topic Expert
0 Kudos

Dear Ashwini,

The assignment of a role to a task or task to a role is working vice versa. This means in detail: the user is selecting a task in the structure tree and is calling tab "roles" where the desired role can be assigned.

When the user is navigatint to "Resources" > "Details" the role can be selected. When calling the tab "tasks" the assigned task from step 1 is

displayed.



The parameters "Responsible Role"/"Responsible Resource" can be maintained on the task-details.

This person does not have to carry out the task.
Details can you find in the online help under:

https://help.sap.com/viewer/DRAFT/213a68a4ef6e448e8e49d8f67d1a1607/6.1.08/en-US/49773e6643043e13e100...